UPDATE - 25 MARCH 2021

Development Victoria is pleased to convey title registration has now been achieved for your purchased lot in construction Stage 1 at Taylors Quarter!

Your conveyancer has been sent letters by Development Victoria confirming title registration of your land.  You can now make preparations for settlement, which is due on 6th April 2021.

You are also now able to make arrangements with your builder to undertake soil testing of your lot.  Access to your lot can be made via Tasman Crescent as Stage 2 and 3 civil construction is still in progress and under the civil contractor’s control.  Please also note when visiting your lot, civil defect rectification is ongoing by the civil contractor as well as landscaping works within the Road Reserve.

If you have any questions about the above information, please send an email to Development Victoria.

 

UPDATE - MARCH 2021

Development Victoria is pleased to confirm that construction Stage 1 at Taylors Quarter has now been issued with a Statement of Compliance from Council. Your purchased lot is within this stage of works.

The Plan of Subdivision has now been lodged at Land Use Victoria for registration, with titles expected to be issued in late March 2021.

Once titles have been issued, your conveyancer will receive a notification confirming that you have 14 days to arrange settlement of your land. There is no obligation to wait until the 14th day, in fact you may arrange to book settlement as soon as titles are received. 

Upon title registration, you will also receive notification of when soil testing by your builder can be undertaken on your lot. 

Civil Construction Progress

construction commences
100% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works. Home construction will commence after civil construction is completed.

Title Registration Progress

75%
complete

settlement
100% - In Progress

Contact made by Development Victoria to purchaser's legal representatives / conveyancers to initiate settlement process (settlement can occur at any time up to 14 days after title registration is achieved). Soil testing by builders and bank valuations can be undertaken at this point.

Title registration
75% - Complete

Document lodged to Land Titles Victoria to enable title registration. Estimated timeframe for title registration following lodgement 10-14 days.

statement of
compliance
50% - Complete

Document received from local council confirming construction has been completed in accordance with approved plans developed by the relevant authorities.